    Sirius Project in Colombia

    Ecopetrol-Petrobras Partner on Sirius Project in Colombia

    Ban LNG Imports from Russia

    Japan Says: Difficult to Ban LNG Imports from Russia

    SM Energy and Civitas Resources

    SM Energy and Civitas Resources Eye Merger Worth US$12.8bn

    EPC Contract for CCS Project

    Samsung C&T Awarded EPC Contract for CCS Project

    Complete Withdrawal from Russian Oil and Gas

    EU Eyes Complete Withdrawal from Russian Oil and Gas Deals

    Khor-Mor-Gas-Field-in-Iraq

    Khor Mor Gas Field in Iraq to Increase Its Output by 50%

    Oil And Gas Discovery in Orange Basin

    Oil and Gas Discovery in Orange Basin Offshore Namibia

    Oil and Gas Needs More Investment

    OPEC+ Stresses that Oil and Gas Needs More Investment

    Rosebank Oil Field Project

    Equinor Makes Fresh Case to Drill Rosebank Oil Field Project

  • Projects
    EPC Contract for CCS Project

    Samsung C&T Awarded EPC Contract for CCS Project

    Khor-Mor-Gas-Field-in-Iraq

    Khor Mor Gas Field in Iraq to Increase Its Output by 50%

    27 Stake by QatarEnergy

    27% Stake by QatarEnergy in North Cleopatra Offshore Egypt

    Tamboran to acquire Falcon Oil Gas

    Tamboran to Acquire Falcon Oil & Gas in Australia

    Subsea Production Systems

    TechnipFMC Gets Petrobras Subsea Production Systems Deal

    Oil and Gas Exploration

    Egypt Signs 3 Deals worth Over $121M for Oil and Gas Exploration

    13bn Worth Iraq Project

    QatarEnergy, TotalEnergies Partner $13bn Worth Iraq Project

    25 Billion LNG Project

    McDermott Gets Key Contract for $25 Billion LNG Project

    4bn New Israeli Gas Offtake Contracts

    Energean Lands $4bn New Israeli Gas Offtake Contracts

  • Whitepapers

    OGA 2017 Post Show Report

    US Polyethylene Export Market Report 2017-2020

    US Polyethylene Export Market Report 2017-2020

    Embedded SSD Flash Management

    Enterprise SSD: More Than Just a New Kind of Hard Drive

    Efficiency, Visibility and Reliability Keys to lower costs and greater profitability in oil and gas operations

    Don’t Miss the Unconventional Resource Revolution’s Next Wave

    Better Safety, Better Business: Maintain Compliance and Drive Revenue: Put All of Your Data to Work

    Breaking the Application Barrier: Why Data is the Most Valuable Asset in the Oil and Gas Industry

    Drilling Optimization Through Advanced Analytics Using Historical and Real-Time Data

  • Press Releases
    Cloudera and Aramco Plan to Collaborate on AI driven Digital Innovation in Saudi Arabia

    Cloudera and Aramco Plan to Collaborate on AI-driven Digital Innovation in Saudi Arabia

    Youth-Empowerment at Namibia Oil and Gas Conference 2025

    Namibia Oil and Gas Conference 2025 Announces Future Generations Masterclass in Partnership with the Namibia Youth Energy Forum

    Alaska LNG

    Glenfarne Announces Over $115 Billion of Strategic Partner Interest for Alaska LNG

    agreements with US companies

    Aramco announces 34 MoUs and agreements with US companies

    Sinopec Sets New Vertical Well Depth

    Sinopec Sets New Vertical Well Depth Record of 5,300 Meters

    Jubail Asset Integrity

    Jubail to Host the 3rd Asset Integrity and Process Safety Conference & Exhibition 2025

    IPTC 2025 Launched: Driving Innovation, Sustainability, and Excellence in Energy

    Ocean Business announces exhibitor list for 2025 show

    Ocean Business 2025 conference programme announced

  • Market Reports
    LongTerm Interests of Russia Saudi Arabia

    OPEC+ Key to Long-Term Interests of Russia, Saudi Arabia

    Oil and Gas Permission

    Oil And Gas Permission Still on During US Shutdown

    AI Technology Maturing the Oil and Gas Workforce

    AI & Technology Maturing the Oil and Gas Workforce

    HDPE Market in Oil and Gas

    HDPE Market in Oil and Gas: Trends and Global Forecast

    Top 5 Oil and Gas Sector Trends that are Active in 2025

    Oil-and-Gas-Analytics

    Oil and Gas Analytics Market Growth Trends and Forecast

    Gas-Transportation

    Transport Capacity – Key to Gas Sector Growth in India

    Offshore-Drilling

    Namibia Showcases its Offshore Drilling Activities

    Global-Oil

    Demand for Global Oil to Grow to Almost 104 mb/d in 2025

  • Events
  • Contact Us
No Result
View All Result
Oil&Gas Advancement
No Result
View All Result
Home Asia Pacific

Queensland Curtis LNG, Australia

in Asia Pacific, Downstream, Projects
Share on FacebookShare on Twitter

The Queensland Curtis LNG (QCLNG) project is located on Curtis Island, Gladstone, in Queensland, Australia, and is being developed by QGC, a BG Group business. The project area starts from Surat Basin in Southern Queensland, extends to Gladstone and Curtis Island, and is spread over 500km.

The project involves conversion of coal seam gas (CSG) reserves into LNG, first of its kind in the world. It also includes expansion of exploration and development of CSG reserves in southern and central Queensland.

The CGS is transported via a 340km underground pipeline network to Gladstone. The gas is then transformed into LNG at the LNG plant on Curtis Island. The CSG to be converted into LNG is supplied to QGC by Origin Energy and its partner ConocoPhillips.

The final investment decision on the project was made in October 2010 after getting project approval from the Queensland Government in June of that year. Construction on the project was launched in late 2010. The production from the first train took place in December 2014, whereas commercial production from the train was achieved in May 2015. The second train is expected to come on stream in the third quarter of 2015.

The new facility will create thousands of jobs with a peak on site construction workforce of over 5,000 and over 700 during operational phase. The project is expected to generate around A$32bn in revenue for Queensland by 2021.

Construction and infrastructure

“The Queensland Curtis project creates thousands of jobs.”

The project development comprises five components, namely the gas field, pipeline, LNG plant, swing basin and channel, and shipping operations. The gas field component involves expansion of coal seam gas operations in Surat Basin.

Approximately 6,000 gas production wells will be developed during the project’s life. Out of 6,000, around 2,000 wells were phased by 2014. The rest will be developed to replace declining wells.

The development and construction of LNG plant, pipelines and gas fields was completed by 2014. The infrastructure for the gas field includes gas and water gathering systems along with gas processing and compression systems. Associated surface equipment consisting of wellhead separators, telemetry devices and metering stations is also being developed.

The LNG plant is being developed over an area of approximately 270 hectares at North China Bay on Curtis Island. The initial LNG plant with two trains will have production capacity of 8.5 million tonnes per annum. The capacity can be extended up to 12 million tonnes per annum. The plant will have three LNG trains or units.

Phase I includes two LNG processing trains. The plant also has gas pre-treatment facilities, a nitrogen rejection unit and two containment LNG storage tanks, each of 140,000m³ capacity. In addition, it has jetty and docking facilities, and a material offloading facility for ferry transportation and receiving construction material.

“Around 6,000 gas production wells will be developed during the project’s life.”

An offloading channel with five berths has been built temporarily to provide access for vessels to the material offloading facility during the project construction. Under the Curtis Spur Channel, the berth pocket, swing basin and a connecting channel is developed. The existing port channels have also been upgraded .

The first LNG is loaded at marine jetty. The next ship transited through Gladstone Harbour and further transited through Great Barrier Reef Marine Park to open ocean.

Queensland Curtis LNG’s pipeline network

The gas is transported through a 540km underground pipeline network in Curtis Island. This includes a 340km export trunk line connecting the gas field to a processing plant facility in Gladstone.

The pipeline is 42in in diameter and is designed to operate at pressures of up to 10.2mpa.

Contracts awarded for the Australian LNG project

The engineering, procurement, and construction contract for the project was given to Bechtel Corporation in July 2008.

Verification services for the development of the LNG project were provided by GL Noble Denton.

Murphy Pipe and Civil Constructions installed gas and water gathering pipelines for all the gas fields owned and operated by QGC in the Surat Basin. The contract was announced in May 2012 and is valued at A$250m.

A joint venture of Transfield and Clough was awarded a contract for the first stage of natural gas processing facilities in October 2012. Under the A$80m contract, the JV provided front-end engineering and planning for gas compression facilities. It was also responsible for bulk earthwork, piling and construction of concrete foundations.

Regular maintenance services on gas field and pipeline facilities of the LNG project are provided by Transfield Services under a contract signed in November 2012.

LNG supply agreements

Supply agreements for around 10mtpa of LNG from the project have been arranged by BG Group to date. Prominent buyers include China National Offshore Oil Corporation (CNOOC), Tokyo Gas, GNL Chile, Chubu Electric, and the Energy Market Authority of Singapore.

An agreement to supply 1.2 million tonnes per annum of LNG to Tokyo Gas for 20 years starting from 2015, along with BG Group’s LNG portfolio, was signed between the two companies in March 2010. Tokyo Gas acquired a 2.5% equity stake in second LNG train of phase I of the LNG plant. The deal was finalised in March 2011.

A sales contract was signed between BG Group and CNOOC and its affiliates in March 2010. As per the agreement, 3.6 million tonnes per annum of LNG from the project will be provided to CNOOC for 20 years starting from 2015.

In October 2012, CNOOC signed a Heads of Agreement (HOA) with BG to acquire certain interests in the LNG project for about $1.93m. Under the HOA, CNOOC acquired 40% interest in the first train of the project.

A 21-year LNG sales agreement was signed between BG Group and Chubu Electric in May 2011.

Previous Post

Matindok Gas Development Project, Central Sulawesi, Indonesia

Next Post

Warro Tight Gas Field, Perth, Western Australia, Australia

Related Posts

Sirius Project in Colombia
Gases

Ecopetrol-Petrobras Partner on Sirius Project in Colombia

November 6, 2025
Ban LNG Imports from Russia
Asia Pacific

Japan Says: Difficult to Ban LNG Imports from Russia

November 6, 2025
EPC Contract for CCS Project
News

Samsung C&T Awarded EPC Contract for CCS Project

November 5, 2025
Complete Withdrawal from Russian Oil and Gas
Gases

EU Eyes Complete Withdrawal from Russian Oil and Gas Deals

November 3, 2025
Khor-Mor-Gas-Field-in-Iraq
News

Khor Mor Gas Field in Iraq to Increase Its Output by 50%

October 24, 2025
Predictable Oil Gas Supply from Norway
News

Oil Giants Prefer Predictable Oil & Gas Supply from Norway

October 17, 2025
Next Post

Warro Tight Gas Field, Perth, Western Australia, Australia

LatestNews

Ban LNG Imports from Russia
Asia Pacific

Japan Says: Difficult to Ban LNG Imports from Russia

November 6, 2025
SM Energy and Civitas Resources
America

SM Energy and Civitas Resources Eye Merger Worth US$12.8bn

November 5, 2025
EPC Contract for CCS Project
News

Samsung C&T Awarded EPC Contract for CCS Project

November 5, 2025
Complete Withdrawal from Russian Oil and Gas
Gases

EU Eyes Complete Withdrawal from Russian Oil and Gas Deals

November 3, 2025
Khor-Mor-Gas-Field-in-Iraq
News

Khor Mor Gas Field in Iraq to Increase Its Output by 50%

October 24, 2025
Oil And Gas Discovery in Orange Basin
News

Oil and Gas Discovery in Orange Basin Offshore Namibia

October 24, 2025
Tashkent Uzbekistan 2026

About Us

Oil & Gas Advancement is a specialized platform delivering latest news and industry insights for the global oil and gas sector. Featuring market intelligence, expert opinions, events and updates, it serves as a trusted and strategic resource for industry stakeholders navigating energy transitions.

Subscribe Us

Resources

  • Advertise with us
  • Contact Us
  • Newsletter Archive
  • Download Mediapack
  • Newsletter Subscription

System

  • Search
  • Site Map
  • RSS Feed
  • Upstream
  • Pipelines & Transport
  • Downstream

© 2025 Copyright Valuemediaservices 2025 All rights reserved.

No Result
View All Result
  • Home
  • News
  • Projects
  • Whitepapers
  • Press Releases
  • Market Reports
  • Events
  • Contact Us

© 2025 Copyright Valuemediaservices 2025 All rights reserved.